King County Navigation Bar (text navigation at bottom)

King County Auditor

Information and Telecommunications Services

Report No. 97-10

Harriet M. Richardson, Principal Management Auditor
Mac Fletcher, Principal Financial Auditor
Nancy McDaniel, Management Auditor
Risa Sandler, Management Intern


TABLE OF CONTENTS

Introduction
Background
Objectives and Scope
General Conclusion
Major Findings:

Finding - Information and Telecommunications Services' restructuring of its rates for 1997 resulted in a fair and reasonable methodology, although other rate calculation methods could potentially reduce the impact on CX-funded agencies.
Finding - Information and Telecommunications Services charged its mainframe and analyst costs for 1997 based on a proposed rate ordinance that had lapsed, rather than the previously adopted rate ordinance.
Finding - The County spent substantially more on a county-wide wan than originally planned. However, the WAN was implemented for significantly more users than originally planned.
Finding - The WAN design team study report was a detailed design plan, but not an adequate budget plan. However, it was the basis of the original decision in 1997 to provide $5.8 million to fund a WAN.
Finding - King County's GIS projects achieved the desired outcomes, within their original budgets, as specified in planning documents.

INTRODUCTION

The management audit of Information and Telecommunications Services (ITS) was requested by the Metropolitan King County Council and included as an amendment to the 1997 Auditor's Office work program. The audit was prompted by council concerns regarding the amount of money spent on technology; the methodology for establishing ITS rates; and that the process used to identify, approve, and implement information technology projects may not ensure that the county received what was proposed, either in terms of the technology itself or expected benefits.


BACKGROUND

The Information and Telecommunications Services Division, in the Department of Information and Administration Services, provides information technology services to other county agencies. These services include computer systems development and processing, technology planning, corporate communications, network services, and maintenance and enhancement of the county's wide area network (WAN). ITS recovers its costs by charging other county agencies for the services it provides. The Information and Telecommunications Services Fund was established as an internal service fund to account for the services that ITS provides to other county agencies.


OBJECTIVES AND SCOPE

The audit objectives were to determine:

  • how ITS expenditures are charged to other county agencies and whether the methodology for allocating such expenditures is fair and reasonable; and
  • whether any differences occurred between what was proposed to be purchased and what was purchased with technology bonds for ITS-managed projects.

The audit was limited to reviewing the methodology used to calculate ITS rates for 1997, as well as identifying what technology the county received, and at what cost, for three information technology projects implemented and managed by ITS. The three projects reviewed were the WAN (which included e-mail), WAN connectivity, and the geographic information system (GIS).


GENERAL CONCLUSION

The general conclusions are that the methodology that ITS uses to allocate the cost of its services to county agencies is fair and reasonable, but that better details are needed regarding project budgets and scope when planning capital investments for information technology projects, and improvements are needed in documenting changes that occur as a project progresses.


MAJOR FINDINGS AND RECOMMENDATIONS

Finding 2.1. Information and Telecommunications Services' restructuring of its rates for 1997 resulted in a fair and reasonable methodology, although other rate calculation methods could potentially reduce the impact on CX-funded agencies.

ITS allocates the cost of services it provides to county agencies using methods that vary according to the type of service provided. During the 1997 budget process, ITS performed a detailed analysis of the methodologies used to allocate its infrastructure and GIS operating and maintenance (O & M) costs among users. This analysis resulted in ITS selecting an infrastructure rate that was based on the number of FTEs for the WAN and the number of e-mail addresses for e-mail costs, and selecting a GIS rate that was based on the number of system licenses. These methods resulted in approximately $2.5 million (35%) of the infrastructure O & M costs and $488,000 (39%) of the GIS O & M costs being allocated to CX-funded agencies. Although audit staff determined that the CX impact for infrastructure O & M costs could have been reduced by $11,569 during 1997 if department FTE counts were adjusted to reflect overtime, extra help, and temporary contract workers, we also determined that the methodologies used were fair and reasonable.

The audit recommended that the Metropolitan King County Council make a policy decision to either accept the methods currently used by ITS to establish cost allocation rates or determine what modifications, if any, should be made in the methodologies to reduce the impact on CX-funded agencies.

Finding 2.2. Information and Telecommunications Services charged its mainframe and analyst costs for 1997 based on a proposed rate ordinance that had lapsed, rather than the previously adopted rate ordinance.

ITS established rates for some of its services in an ordinance that became effective in January 1994. In 1996, ITS developed a new rate ordinance that recommended both rate increases and decreases. Although the proposed ordinance was introduced but lapsed without being adopted, ITS began charging the rates in the proposed ordinance rather than continuing to use the rates established in the adopted ordinance. However, audit staff also found that ITS was the only internal service fund agency that established its rates by ordinance, and that rescinding the portion of the rate ordinance that applies only to support of other county departments would provide ITS with more flexibility in being able to adjust its rates as necessary.

The audit recommended that ITS draft an ordinance to rescind the sections of the current rate ordinance that pertain to rates charged only to county agencies and revise the fees for services provided only to external users.

Finding 3.1. The County spent substantially more on a county-wide wan than originally planned. However, the WAN was implemented for significantly more users than originally planned.

The Information Services Division in the former Department of Metropolitan Services began installing the WAN infrastructure in early 1995 with a $5.8 million budget appropriation. When the council authorized a technology bond in December 1995 to fund the WAN, the estimated cost of the WAN had increased to $8.4 million (including $1.2 million for e-mail), and a parallel project, WAN connectivity, had been added with a budget of $3.3 million. Although the project plan stated that 82 sites would be connected to the WAN, and the appropriation documents increased that to 93 sites, a total of 127 sites had been connected and 14 more were in the process of being connected by August 1997. Additionally, 7,746 employees had e-mail access, although e-mail was not included in the original planning documents and the appropriation documents anticipated only 4,000 e-mail users.

Based on the estimated number of WAN and e-mail users, the appropriated budget amount represented an average cost of $90,000 for each site connected to the WAN and $300 per e-mail user. However, the actual costs averaged $52,000 per site, or 57.8% of the estimated cost, and $176 per e-mail user, or 58.7% of the estimated cost. Based on the significant differences between the estimated and actual costs, audit staff concluded that the cost estimates developed in the planning phase of the project were unsatisfactory.

Finding 3.2. The WAN design team study report was a detailed design plan, but not an adequate budget plan. However, it was the basis of the original decision in 1997 to provide $5.8 million to fund a WAN.

The planning document for the WAN infrastructure project was the Design Team Study Report, completed in April 1994. Audit staff found that although the report was a detailed design document, it lacked important budget information. For example, the report did not break out capital and operating costs and it provided only rough cost estimates (i.e., rounded numbers with little detail to back them up). Moreover, although changes were made in the scope of the project after the Design Team Study, these changes were not well documented or referenced back to the original plan. These deficiencies limited the ability of audit staff to track changes in the project's scope and costs and determine the reasonableness of the original cost estimates and actual expenditures.

The audit recommended that ITS establish policies and procedures to ensure better planning, tracking and accountability for all information technology capital projects. Such procedures should require consistent use of a project plan that clearly describes the project's scope, details the project's estimated capital and operating costs, establishes a format for tracking project expenditures, and requires that subsequent changes to a project's scope be referenced back to the original plan to facilitate tracking of changes in scope or costs.

Finding 4.1. King County's GIS projects achieved the desired outcomes, within their original budgets, as specified in planning documents.

A Coordinated Scoping Document, with a total budget of $9.2 million, was developed in 1993 to serve as a guide for implementing GIS in the consolidated King County-Metro government. A subsequent GIS plan was created in 1994 that provided detailed steps and timelines for acquiring a GIS but did not include either comprehensive references to the projects and deliverables cited in the Scoping Document or a budget. However, audit staff determined that the deliverables outlined in the Coordinated Scoping Document and several additional interface capabilities were realized. Audit staff also determined that the GIS was implemented with over $546,000 remaining from the total available funds.


Updated: 06/24/02

Auditor's Home | Audit Reports | Contact Us | Links to Audit Related Sites

King County | News | Services | Comments | Search

 

Links to external sites do not constitute endorsements by King County.
By visiting this and other King County web pages,
you expressly agree to be bound by terms and conditions of the site.
The details.