Conditional use permit (CUP)
What is the purpose of a conditional use permit?
A conditional use permit (CUP) allows the county to consider uses that may be desirable to a particular community, but which are not routinely allowed, through a public hearing process, and to control certain uses which could have detrimental effects on a community or neighboring properties. A 'conditionally permitted use' on a specific property is subject to conditions that ensure compatibility with nearby land uses.
The conditional use permit process allows for consistent evaluation of land use applications and provides clear criteria on which to base a decision. The burden is on the applicant to provide adequate justification supporting a CUP request.
What activities require this permit?
- Refer to 21A.08* of the King County Code (KCC) at www.metrokc.gov/council/code to determine whether a proposal requires a CUP.
- For minor communication facilities (including cell towers), refer to KCC 21A.26*.
How much will it cost?
See DDES' current fee schedule for an estimate.
Where can I get an application?
- Refer to the Conditional Use Permits Packet for application materials
- Request an application packet by mail by calling DDES customer service at 206-296-6600 or
- Pick up an application packet at DDES in Renton (see map and directions).
How do I submit my application?
See information on pre-applications as a pre-application meeting is required prior to filing a CUP application.
The CUP application must be filed in person at the DDES Permit Center. An appointment with a Zoning Technician is required to file the application. Call 206-296-6797 to schedule the appointment. For more information, refer to Applying for a permit at DDES.
What is the timeline for processing a conditional use permit?
- DDES Land Use Services Division (LUSD) staff will schedule a pre-application meeting within 30 days from the date of the request.
- LUSD staff has 28 days from the date the application is filed to determine whether the application is complete.
- After LUSD staff determines that a CUP application is complete, a Notice of Application is issued. The minimum public comment period is 21 days.
- The process to make a final decision on a CUP generally takes 120 days provided no appeals are filed or substantial additional information is required.
What is the appeal process?
Refer to permit type 2. There is a 14-day appeal period whereby an aggrieved person can file an appeal together with an appeal filing fee to the King County Hearing Examiner.
Notes / Comments
For more information, see Type 1-4 Applicant Designation.
Legal authority
Title 21A of the King County Code
Administered by
DDES Land Use Services Division
Contact
For questions, please contact DDES customer service at 206-296-6600.