Recycled Product Experience:

Recycled Glass Aggregate, Roads Division

Product and recycled content 100% recycled glass cullet
Application Retaining wall backfill
replaces gravel
Location/Date Des Moines Memorial Drive/S. 99th St
July, 1998
Project manager/user Ryan Shular, P.E, Senior Engineer
King County Roads Division, (206)296-8783
Architect/Engineer Michael Burk, Engineer
King County Roads Division, (206)296- 8886
General Contractor Dennis R. Craig Construction, Inc
Vern Endres, Project Manager, (206)882- 2922
Background, history have used before in same application
Performance No substantial difference in performance
Source of material Fibres International
Toni Rounds, (206)762-8520
Quantity 300 tons
3/4" minus glass cullet
Cost $16.00 per ton
Cost savings or increase No significant difference
Installation, costs/savings Somewhat more difficult to handle than conventional gravel aggregate
Source of extra funds N/A
Would you buy this product again? Yes.
Why or why not? Recycled glass aggregate provides comparable performance to conventional aggregate in some applications
Comments

For more information about this product:


E-mail

Return to Environmental Purchasing Menu | Product Experience List

Updated: October 23, 1998


King County | News | Services | Comments | Search

Links to external sites do not constitute endorsements by King County.
By visiting this and other King County web pages,
you expressly agree to be bound by terms and conditions of the site.
The details.